February 2012 - Throughout December and January work continued on our new production facility to ensure the August deadline will be met.
As the photos show we now have walls, windows and a roof. Which is a great relief to those working on the building as Danish winters are known to be a touch brisk.
November 2011 - Due to an increased demand for larger bespoke lifts, production will be moved into a new facility adjoining the current production unit in North Juntland, Denmark. The new High Bay production facility will be complete with overhead cranes to handle the larger components.
As well as manufacturing the larger bespoke lifts, the new facility will also include a testing area for the increasingly popular MastLyft free standing goods lift.
The production of the smaller & standard scissor lifts will remain at the current factory. A result of the production of the larger lifts being moved is that the efficiencies and fast delivery schedules of our standard range can be maintained.
TRANSLYFT started construction back in August 2011 and aims for the new production facility to be up and running later this year